Why Indore’s Bada Ganpati flyover may not be ready by 2028

Why Indore’s Bada Ganpati flyover may not be ready by 2028
Why Indore’s Bada Ganpati flyover may not be ready by 2028

REPORTED BY

Follow our coverage on Google News

The Bada Ganpati flyover project in Indore has faced a major delay. A large underground sewer line is blocking the way, and it’s taken two years to get approval to shift it. This delay now puts the 2028 deadline in doubt.

A 1400 mm-wide primary sewerage line runs right under the flyover’s planned central pillars. This line is about 30 feet deep and passes through the entire median. The foundation of each bridge pillar also needs to be built 15 to 20 feet deep. Since the line is exactly at that depth, redesigning the bridge is not an option.

After four months of back-and-forth, the Municipal Corporation has approved the plan to shift the line. The work will use trenchless and micro-tunneling technology. This method avoids open digging and helps reduce the risk of soil collapse. The total cost will be around ₹10.5 crore. The process will take 6 to 8 months and is expected to begin after the 2025 monsoon.

This sewer line isn’t the only one causing trouble. A second 1200 mm line also connects to it. Both lines handle large amounts of sewage from different parts of the city. The shifting will be difficult because of the limited space. Nearby lines may also need to be moved, adding to the complexity.

  • Space is limited. There’s barely any room around the line.

  • Political delays held up permissions.

  • Soil collapse is a serious risk if digging is not handled carefully.

  • A second 1200 mm line connects to this one, adding complexity.

The Indore Development Authority (IDA) had hoped to complete the bridge before Simhastha 2028. A tender and work order were issued in 2024. But with the line shifting work starting late 2025 or early 2026, the actual bridge work will begin much later than planned. That leaves just two years for construction.

IDA CEO Ramprakash Ahirwar confirmed that the sewer shifting has board approval and that funds will be released once final estimates are in. Municipal Commissioner Shivam Verma said the corporation is ready to start work as soon as the IDA gives the green light.

Until the sewer line is moved, construction can’t begin. And with the schedule already tight, meeting the 2028 deadline looks increasingly difficult.

Support us to keep independent environmental journalism alive in India.

Keep Reading

Short circuits, long suffering: MP’s farm fire tragedies

Sun-kissed farmers: Promises and problems of MP’s solar pumps

How a hydro project in shahabad forest threatens india’s Cheetah Corridor

Scorching Schools: MP’s poor infrastructure puts kids at risk in heatwaves

Follow Ground Report on X, Instagram and Facebook for environmental and underreported stories from the margins. Give us feedback on our email id greport2018@gmail.com

Don’t forget to Subscribe to our weekly newsletter, Join our community on WhatsApp, and Follow our YouTube Channel for video stories.

Author

Related

Support Ground Report to keep independent environmental journalism alive in India

We do deep on-ground reports on environmental, and related issues from the margins of India, with a particular focus on Madhya Pradesh, to inspire relevant interventions and solutions. 

We believe climate change should be the basis of current discourse, and our stories attempt to reflect the same.

Connect With Us

Send your feedback at greport2018@gmail.com

Newsletter

Subscribe our weekly free newsletter on Substack to get tailored content directly to your inbox.

When you pay, you ensure that we are able to produce on-ground underreported environmental stories and keep them free-to-read for those who can’t pay. In exchange, you get exclusive benefits.

Your support amplifies voices too often overlooked, thank you for being part of the movement.

LATEST

mORE GROUND REPORTS

Environment stories from the margins